ONGOING PROJECTS
Will take precedence over all

other installs at critical times:

  • Software upgrades: In process; please request on a case-by-case basis via the LSO Request for New Support .
    * Eudora Pro email software
    * Microsoft Office 97 software (Word, Excel, Powerpoint, Access)
    * MeetingMaker scheduling software

·         Terminal Replacements:
All "dumb" terminals (IBM 3151, 3164) are being replaced, with a target completion date of 7/31/2001.

·         Public printer reconfiguration:
Public workstation printers will be selectively consolidated to improve reliability and reduce support overhead.

·         MSW replacements:
All DOS-based Multisession Workstations are being phased out, with a target date of Spring, 2001. Approximately 55 of these workstations remain as of  December, 2000.

 

INSTALLS IN PROCESS

  1. Geology: ABLE Workstation [Install 419]: Ptak- Deployment planning in process, 12/14/2000
  2. Collection Management: 1 Chimera/ABLE Workstation- Deployment planning in process, 12/14/2000
  3. Lehman: 1 Chimera/ABLE Workstation [Install 443]- Deployment planning in process, 12/14/2000
  4. Avery: 1 Chimera/ABLE Workstation- Awaiting site plan, 9/29/2000
  5. East Asian: 1 Chimera/ABLE Workstation [Install 425]- Deployment planning in process, 12/14/2000
  6. Music: 1 Chimera/ABLE Workstation [Install 564]- Deployment planning in process, 12/14/2000
  7. Mono Recon: 1 Chimera workstation with new Se-lin labeler: Equipment order in process, 12/14/2000
  8. Butler Reference: 1 Chimera/ABLE Workstation [Install 509]- Deployment planning in process, 12/14/2000
  9. Lehman: Reserves scanning workstation [Install 557]: Equipment being configured, 12/14/2000
  10. Lehman: Relocation [Install 558]- CTS will schedule 
  11. Preservation: 3 TSW upgrades: Lowe [Installs 510-512]- Equipment orders in process, 12/14/2000
  12. Music: MOSIS: E. Davis [Install 508 2000/01 Equipment Request HH7]- Equipment order in process, 12/14/2000
  13. H&H: MOSIS Upgrade: DeDonato [Installs 553, 2000/01 Equipment Request HH1]- Deployment planning in process, 12/14/2000
  14. H&H: MOSIS Upgrade- Stuveras [Installs 555, 2000/01 Equipment Request HH6]: Deployment planning in process, 12/14/2000
  15. Financial Services: MOSIS upgrade- Reiter [Installs 559, 2000/01 Equipment Request HR/F3]: Deployment planning in process, 12/14/2000
  16. Collection Management: 2 MSW upgrades: Austin [Installs 530-531]- Upgrades to take place with other Butler MSWs, ie. By mid-January, 2001
  17. MRR: MSW upgrade: Austin [Install 532]- Upgrades to take place with other Butler MSWs, ie. By mid-January, 2001
  18. MPS: 2 MSW upgrades- Bicsak [Install 513-514]- Upgrades to take place with other Butler MSWs, ie. By mid-January, 2001
  19. MRR: MOSIS Plus: Austin [Install 548, 2000/01 Equipment Request AC3]- Equipment order in process, 10/26/2000
  20. Music: Second CLIO Circ. PC [Install 565]: Patterson- Equipment order in process, 12/14/2000
  21. Engineering: 2 Netstations to replace CLIO OPAC: Site plans received, Deployment planning in process, 12/14/2000
  22. ILL: Netstation- K. Davis [Install 437]: Deployment planning in process, 12/14/2000
  23. LSO: Scan Station upgrade: Caldano- Deployment planning in process, 12/14/2000
  24. Chemistry:  RWS Upgrade- Nagaraja [Install 549, 2000/01 Equipment Request SC3]- Equipment order in process, 10/26/2000
  25. Geology:  RWS Upgrade- Fish [Install 550, 2000/01 Equipment Request SC4]- Equipment order in process, 10/26/2000
  26. Engineering: MOSIS Plus- Ptak [Install 551, 2000/01 Equipment Request SC2]- Equipment order in process, 10/30/2000
  27. Lehman: GPO Access upgrade: Breeze [Installs 491, 2000/01 Equipment Request SO1]- Equipment order in process, 12/14/200
  28. RBML: Reconfiguration- Ellenbogen [Install 529]: CTS will schedule
  29. Butler Reference: 4 CD-Standalone upgrades: Stuveras [LSO-Installs 352-355]- Pending outcome of CD-LAN expansion, 7/19/2000
  30. Butler Access: 2 Stack Lookup terminals: Austin (installs 460-461)- Site plans received, installs postponed until 12/2000
  31. Butler Access: 2 new MOSIS for Circulation: Dawes [Installs 545-6, 2000/01 Equipment Request AC1 and AC2]- Equipment order in process, 10/9/2000
  32. Butler Access: new MOSIS for LIO: Dawes [Install 547; 2000/01 Equipment Request AC3]- Equipment order in process, 10/9/2000
  33. RBML: TSW on laptop: Ellenbogen [Install 540]: Equipment order in process, 11/20/2000
  34. Science Division: MOSIS on laptop [2000/01 Equipment request SC3]: Equipment order in process, 11/20/2000
  35. Oral History: 4 MOSIS workstations replacing older PCs [Installs 560-563]: Equipment orders in process, 12/14/2000
  36. Avery: 2 laserjet 4050N printers for Netstations: Awaiting site plan, 12/14/2000
  37. East Asian: 5 Netstations, 2 Laserjet 4050N printers and 1 CLIO Plus Lite PC to replace CLIO Plus terminals: Awaiting site plans, 12/14/2000
  38. Rare Books: 1 Netstation and 1 Laserjet 4050N printer to replace CLIO Plus terminal: Awaiting site plan, 12/14/2000
  39. Engineering: 3 Laserjet 4050N printers to replace individual Netstation printers: Awaiting site plans, 12/14/2000
  40. Biology: 1 Netstation and 1 Laserjet 4050N printer to replace CLIO Plus terminal: Awaiting site plan, 12/14/2000
  41. Psychology: 1 Netstation, 1 Laserjet 4050N printer and 1 CLIO Plus Lite PC to replace CLIO Plus and CD-LAN terminal: Awaiting site plan, 12/14/2000
  42. Physics: 1 Netstation and 1 Laserjet 4050N printer to replace CLIO OPAC and CL-LAN terminal: Awaiting site plan, 12/14/2000
  43. Chemistry: 2 Netstations and 3 Laserjet 4050N printers to replace CD-LAN terminal: Awaiting site plan, 12/14/2000
  44. Math: 1 Netstation and 1 CLIO Plus Lite PC to replace CLIO Plus terminal: Awaiting site plan, 12/14/2000
  45. Geology: 1 Netstation and 1 Laserjet 4050N printer to replace CD-LAN terminal: awaiting site plan, 12/14/2000
  46. Lehman: 3 Nestations, 3 Cnets and 5 HP Laserjet 4050N printers to replace CLIO Plus terminals: Awaiting site plans, 12/14/2000
  47. Area Studies: 1 HP Laserjet 4050N to replace individual Netstation printers: Awaiting site plans, 12/14/2000
  48. Business: 5 HP Laserjet 4050N printers to replace individual Netstation printers: Awaiting site plans, 12/14/2000
  49. Butler Reference: HP Laserjet 4050N, possibly with Copico interface, for unmediated public printing from Netstation: Awaiting site plan, 12/14/2000
  50. H&H/Anc. Med. Reading Room:  2 Nestations and 1 HP Laserjet 4050N to replace CLIO Plus and CD-LAN terminals: Awaiting site plan, 12/14/2000
  51. H&H/Butler Reserves: 3 HP Laserjet 4050N to consolidate Netstation printing across from desk and in 208: Awaiting site plans, 12/14/2000
  52. Music: 1 Netstation, 1 Laserjet 4050N printer and 1 CLIO Plus Lite PC to replace CLIO Plus terminals: Awaiting site plans, 12/14/2000
  53. Butler Access: Color Printer- Austin [2000/01 Equipment Request AC5]: Awaiting site plan, 12/14/2000
  54. Biology: Color Printer- Kehoe [2000/01 Equipment Request SC1]: Awaiting site plan, 12/14/2000

 