COLUMBIA VRA APEX - SASKIA Collection
Project Start: Project Finish:
Fri 12/12/04 Mon 4/12/04
Tasks
ID
Task Name
Duration
Start
Finish
Resource Names
% Complete
1
Columbia VRA -APEX - Saskia Collection
86.13 days
Fri 12/12/03
Mon 4/12/04
3%
2
Receive data
1 day
100%
3
Receive images
Mon 12/15/03
4
External test
5 days
Wed 1/21/04
Tue 1/27/04
0%
13
Remote install
4 days
Mon 3/22/04
Thu 3/25/04
15
Install on site & training
Tue 3/30/04
Fri 4/2/04
16
Meet & greet/install finalization
0.5 days
17
Admin training
1.5 days
Wed 3/31/04
18
Collection management training
Thu 4/1/04
19
User training
20
Post mortem meeting
1 hr