COLUMBIA VRA APEX - SASKIA Collection





Project Start:
Project Finish:

Fri 12/12/04
Mon 4/12/04




Tasks


ID

Task Name

Duration

Start

Finish

Resource Names

% Complete

1

Columbia VRA -APEX - Saskia Collection

86.13 days

Fri 12/12/03

Mon 4/12/04

 

3%

2

Receive data

1 day

Fri 12/12/03

Fri 12/12/03

 

100%

3

Receive images

1 day

Mon 12/15/03

Mon 12/15/03

 

100%

4

External test

5 days

Wed 1/21/04

Tue 1/27/04

 

0%

13

Remote install

4 days

Mon 3/22/04

Thu 3/25/04

 

0%

15

Install on site & training

4 days

Tue 3/30/04

Fri 4/2/04

 

0%

16

Meet & greet/install finalization

0.5 days

Tue 3/30/04

Tue 3/30/04

 

0%

17

Admin training

1.5 days

Tue 3/30/04

Wed 3/31/04

 

0%

18

Collection management training

1 day

Thu 4/1/04

Thu 4/1/04

 

0%

19

User training

1 day

Fri 4/2/04

Fri 4/2/04

 

0%

20

Post mortem meeting

1 hr

Mon 4/12/04

Mon 4/12/04

 

0%