Butler Library Renovation


Search the Catalog:
Go To CLIO >>

Schedule for Completed Spaces



FALL 2000
  • East passenger elevators
  • Stacks 7 & 8
SPRING 2001 - 4th Floor
  • Periodicals & Microforms Reading Room
SUMMER 2001 - 4th Floor
  • Balance of Philip L. Milstein Family College Library Reading Rooms
FALL 2001 - 5th Floor
  • 5th Floor Offices & Meeting Rooms
  • Stacks 9 & 10
  • West passenger elevator
SUMMER 2002 - 5th Floor
  • Electronic Publishing Initiative at Columbia (EPIC)
  • Columbia Center for New Media Teaching & Learning (CCNMTL)
FALL 2002 - 5th Floor
  • Research Reading Rooms (3)
  • Stack 11
SPRING 2003 - 6th Floor
  • RBML Workroom & locker room
  • New Stairs to 7th floor post M-Phil research space (E & W)
SUMMER 2003 - 6th Floor
  • Research Reading Rooms (5)



Butler Library 
Bullet  Renovation HomePage
Bullet  This Month's Work
Bullet  Renovation Newsletter
Bullet  Phase 1 (Completed)
Bullet  Phase 2 (Completed)
Bullet  Phase 3 (Completed)
Bullet  Phase 4 (Completed)
Bullet  Phase 5 (In Progress)
Bullet  History
Bullet  Project Team

Email:
cul.butler.ren
@libraries.cul.columbia.edu