Schedule for Completed Spaces



FALL 1998 - 2nd Floor
  • Lounge and coffee bar
  • CUIT Butler Computer Lab
  • Information Resources Training Lab
  • Undergraduate Reading Room (North)
  • Lobby
  • Library Information Office
  • Reserves Desk and staff area
  • Undergraduate Reading Room (former College Reading Room; late October completion)
  • Stack Levels 3 and 4 (October completion)
  • Public lockers
  • Photocopy Services Sales area

SPRING 1999 - 2nd Floor
  • Undergraduate Reading Room (current Philosophy Reading Room)
  • Butler Media Center
  • Public Services Directors offices
  • Undergraduate and Assistant Undergraduate Librarian offices
  • Library Systems Offices
  • West Undergraduate Reading Room (May 1999)

FALL 1999 - 2nd Floor
  • Information Resources Training Center
  • Columbia Center for New Media Teaching & Learning

SPRING 2000 - 3rd Floor
  • Lawrence A. Wien Reference Room
  • Circulation Desk and staff areas
  • Undergraduate Reading Room (will continue as Periodical Reading Room until Phase 3 is completed)

JUNE 2000 - 3rd Floor
  • Catalog Room
  • Electronic Text Service
  • Information Resources Training Lab
  • Interlibrary Loan
  • Reference and Collection Maintenance staff areas
  • Undergraduate Reading Room (former Browsing Room)



Butler Library 
Bullet  Renovation HomePage
Bullet  This Month's Work
Bullet  Renovation Newsletter
Bullet  Phase 1 (Completed)
Bullet  Phase 2 (Completed)
Bullet  Phase 3 (Completed)
Bullet  Phase 4 (Completed)
Bullet  Phase 5 (In Progress)
Bullet  History
Bullet  Project Team