Butler Library Renovation


Search Library Catalog:
Go To CLIO >>
  May 12-16, 2008 

Lanterns

The main entrance will be open as usual all week.  Scaffolding at the front door will be removed by Monday.  The lantern installation will be completed after commencement. 

Roof Work

The construction storage container and scaffolding along 114th Street and on the West side of the building will be permanently removed by the end of the week.  Removals, repairs and *noise* continue on the upper roofs.

HVAC Balancing

Repair work on the 1st floor has been completed.  Balancing will resume shortly.

114th Street Marquees

Marquee restoration will resume after commencement.

******************

Construction, including carpentry, continues on Stack 15 and the 8th & 9th floors all week.

May 19-22: Use the temporary East entrance due to commencement activities taking place on the Butler plaza and lawns.

 



We appreciate your patience with any inconvenience.

Normal construction hours are
Monday - Friday, 7:00 am - 3:00 pm

Except where noted, all areas and services remain accessible.
All finishes & cleaning solutions have been approved by Columbia University Environmental Health & Safety Department.

Butler Library 
Bullet  Renovation HomePage
Bullet  This Week's Work
Bullet  Renovation Newsletter
Bullet  Phase 1 (Completed)
Bullet  Phase 2 (Completed)
Bullet  Phase 3 (Completed)
Bullet  Phase 4 (Completed)
Bullet  Phase 5 (In Progress)
Bullet  History
Bullet  Project Team

Email:
cul.butler.ren
@libraries.cul.columbia.edu