Planning includes a set of milestones that can be used to track and view the progress of the APIS I/O System. The milestones are based on the deliverables from the Analysis section.

4.1 Milestones and Deadlines for V1.0

  • Project Plan (Date: 10/20/2003) - Done
  • Initial Design & Requirements (Date: 11/01/2003) - Done
  • Interface Design (Date: 01/23/2004) - Done
  • Detailed Rules and Requirements (Date: 01/30/2004) - Done
  • Technology Framework | JAVA classes (Date: 02/27/2004) - Done
  • Finish Dev | servlets, jsp, & beans (Week of 5/24/2004) - In Process
  • Begin QA/User Testing (Week of 05/31/2004)
  • Launch MMF IU Beta/Alpha (Week of 06/07/2004)


 