4.1 Milestones and Deadlines for V1.0
- Project Plan (Date: 10/20/2003) - Done
- Initial Design & Requirements (Date: 11/01/2003) - Done
- Interface Design (Date: 01/23/2004) - Done
- Detailed Rules and Requirements (Date: 01/30/2004) - Done
- Technology Framework | JAVA classes (Date: 02/27/2004) - Done
- Finish Dev | servlets, jsp, & beans (Week of 5/24/2004) - In Process
- Begin QA/User Testing (Week of 05/31/2004)
- Launch MMF IU Beta/Alpha (Week of 06/07/2004)
|
|